The County of Lennox and Addington has contracted GIP Paving Inc. to construct a roundabout at the intersection of County Road 6 and County Road 23.

The construction involves drainage improvements (ditching, sanitary, culverts), road excavation, localized road widening, concrete curb/sidewalk, electrical lighting, guiderail, landscaping, and asphalt paving.

To facilitate the work, traffic will be reduced to one lane in multiple locations with the use of flag personnel. Advanced notification will be provided if work will impact your driveway. This work is planned to commence on Monday, June 10th, 2024, and is scheduled to be completed by Thursday, October 31st, 2024.

We apologize for any inconvenience this may cause and appreciate your patience over the summer months.

Should you have any questions or require further information please contact:

Brady Dacosta, Site Supervisor, Green Infrastructure Partners Inc. T:343.363.6431 

Dan Fencott, Contract Administrator, Jewell Engineering T: 613.389.7250 x.207