Traffic, Roads, & Bridges

R.W Tomlinson Inc has been contracted by the County of Lennox & Addington to rehabilitate two sections of County Rd 6, one in Loyalist Township and one in the Township of Stone Mills.  The southern section (Loyalist) is from County Road 28 (Millhaven Rd) in Odessa to the CN Rail tracks. The northern section (Stone Mills) is from Wilson Rd to County Road 1 in Yarker.

The rehabilitation generally consists of drainage improvements (ditching & culverts), in-place pulverizing of the existing asphalt, adding granular material and re-paving including paved shoulders. 

To facilitate the work, temporary lane closures will be required and some traffic delays can be expected. 

The work is scheduled to start on approximately August 3rd and is scheduled to be completed by approximately October 29.

We apologize for any inconvenience this may cause and appreciate your patience.